Recently, the energy storage project of China Huadian Corporation began construction. The station was co-located with the Shanxi Datong No. 1 Thermal Power Plant and adopted the latest all-outdoor prefabricated cabin design, using LFP lithium-ion batteries for its 150MW/300MWh BESS, and was connected to the grid by the transformer substation and power lines built by the thermal plant. After the project goes online, it will become the first large-scale and centralized lithium-ion battery energy storage station in Shanxi Province.
150MW/300MWh BESS for Thermal Plant of China Huadian Corporation Began Construction in Datong