China commissioned 3.16 GW / 10.42 GWh of new energy storage capacity in October 2026, up 9% in power capacity and 52% in energy capacity year on year, but down 31% and 28%, respectively, from September.
While monthly installations moderated, the average duration of newly commissioned projects reached 3.30 hours, remaining above three hours for the fourth consecutive month since July. This was substantially higher than the 2.71-hour average for the operating fleet.
The recently released implementation plan for new energy storage during the 15th Five-Year Plan period sets a national average storage duration target of approximately three hours by 2030. Alongside the rollout of capacity pricing and dependable capacity compensation mechanisms, the basis for valuing energy storage is shifting from installed power capacity toward dependable capacity and peak-demand support.
October’s data highlights this transition across deployment volumes, applications, regions, revenue mechanisms, and technologies.
Key Figures
3.16 GW / 10.42 GWh: Newly commissioned capacity, up 9% / 52% year on year.
73.7%: Independent energy storage’s share of newly commissioned power capacity, up eight percentage points year on year.
62%: Northwest China’s share of newly commissioned energy capacity, with an average duration of 4.34 hours.
3.30 hours: Average duration of newly commissioned projects, compared with approximately 2.37 hours a year earlier.
8.2%: Combined share of newly commissioned power capacity accounted for by compressed air energy storage and molten salt thermal storage.
Figure 1. Newly commissioned new energy storage capacity in China, October 2026.
Source: CNESA DataLink Global Energy Storage Database.
Note: Year-on-year changes compare with the same month of the previous year; month-on-month changes compare with the preceding month.
1. Deployment: Average Duration Exceeds Three Hours for Four Consecutive Months
According to preliminary statistics from the CNESA DataLink Global Energy Storage Database, China commissioned 3.16 GW / 10.42 GWh of new energy storage capacity in October. Power and energy capacity increased by 9% and 52% year on year, respectively, while declining by 31% and 28% month on month.
Generation-side and grid-side projects together accounted for 3.07 GW, or 97% of newly commissioned power capacity, with an average duration of 3.33 hours.
Duration is becoming an increasingly significant indicator. At the end of September, China’s cumulative operating new energy storage fleet had an average duration of 2.71 hours. Newly commissioned projects, however, have averaged more than three hours for four consecutive months since July.
October’s average of 3.30 hours was 0.93 hours higher than a year earlier, representing approximately 39% more energy capacity per unit of power capacity. New projects are consistently being designed for longer discharge durations than the existing fleet.
On November 13, 2026, the National Development and Reform Commission and the National Energy Administration released the Implementation Plan for New Energy Storage during the 15th Five-Year Plan Period. The plan targets 300 GW of installed new energy storage capacity nationwide by 2030, with an average duration of approximately three hours.
It also encourages long-duration storage on the grid side and envisages approximately 140 GW of independent grid-side new energy storage capable of supporting supply during peak demand.
Figure 2. Monthly newly commissioned new energy storage capacity and average duration in China, January–October 2026.
Source: CNESA DataLink Global Energy Storage Database.
2. Applications: Independent Storage Retains a 73.7% Share as Generation-Side Duration Rises
Independent energy storage added 2.33 GW / 6.74 GWh in October, up 21% / 41% year on year but down 40% / 47% month on month.
It accounted for 73.7% of newly commissioned power capacity. Although this share fell by 12 percentage points from September’s high base, it remained eight percentage points above the previous year. Independent storage retained its dominant position.
Generation-side storage added 738 MW / 3,482 MWh, up 28% / 196% year on year and 36% / 141% month on month.
Storage paired with renewable generation accounted for 696 MW / 3,403 MWh, or 94.3% of generation-side additions by power capacity. These projects grew by 21% / 190% year on year and had an average duration of 4.89 hours.
The average duration of all generation-side additions reached 4.72 hours, compared with 2.04 hours in October 2025. The shift beyond two-hour configurations adopted primarily to meet storage requirements is one of this year’s clearest changes.
Behind-the-meter storage added 95 MW / 202 MWh, down 74% / 73% year on year but up 18% / 19% month on month. Commercial and industrial projects represented 91.9% of this segment’s newly commissioned power capacity.
East China accounted for 87% of behind-the-meter additions by power capacity. Anhui led provincial deployment with 50 MW / 100 MWh, representing 52.6% of the national total by power capacity.
Figure 3. Application mix of newly commissioned new energy storage projects in China, October 2026, by power capacity.
Source: CNESA DataLink Global Energy Storage Database.
Note: Other applications include distribution transformer service areas, thermal power–storage projects, EV charging stations, mining and oilfield sites, remote areas, commercial buildings, communities, and municipal facilities.
3. Regional Deployment: Northwest China Accounts for 62% of Energy Capacity
Northwest China commissioned 1.49 GW / 6.49 GWh, accounting for 47.2% of national additions by power capacity and 62% by energy capacity. Its average duration reached 4.34 hours, and the region ranked first in both power and energy capacity additions.
East China presented a contrasting profile. It added 805 MW / 1,612 MWh, ranking second by power capacity with a 25.5% national share, but its average duration was just 2.00 hours.
The five leading provinces by newly commissioned energy capacity were:
ProvinceEnergy capacity addedAverage durationGansu3.00 GWh4.00 hoursQinghai1.40 GWh8.75 hoursNingxia1.24 GWh2.70 hoursHebei1.20 GWh3.00 hoursShandong1.11 GWh2.00 hours
Duration distinguishes even provinces with similar energy capacity additions. Hebei commissioned 400 MW / 1,202 MWh, with an average duration of three hours, while Shandong added 553 MW / 1,106 MWh, averaging two hours.
Resource-rich regions increasingly require greater energy capacity and longer discharge durations, while major load centers place greater emphasis on power capacity. These two markets are developing distinctly different project configurations.
Figure 4. Regional distribution of newly commissioned new energy storage projects in China, October 2026.
Source: CNESA DataLink Global Energy Storage Database.
Note: The Southern Region comprises Guangdong, Guangxi, Guizhou, Hainan, and Yunnan. Other regions include Henan, Heilongjiang, Hunan, Hubei, and other provinces.
Figure 5. Top ten provinces by newly commissioned new energy storage energy capacity, October 2026.
Source: CNESA DataLink Global Energy Storage Database.
4. Revenue Mechanisms: Discharge Duration Determines Capacity Compensation
On January 30, 2026, the National Development and Reform Commission and the National Energy Administration issued the Notice on Improving the Generation-Side Capacity Pricing Mechanism (NDRC Price〔2026〕No. 114).
The notice established a national framework for capacity pricing for independent grid-side new energy storage. Local authorities may provide capacity payments to eligible independent grid-side stations that do not participate in storage allocation arrangements.
Capacity payment rates are based on local coal-fired power capacity payment standards and adjusted according to the storage station’s ability to support peak demand.
The adjustment factor is calculated as:
Continuous discharge duration at full power ÷ the longest annual net-load peak duration, capped at 1.
Provincial mechanisms use different peak-duration benchmarks:
Benchmark durationProvinces and regions6 hoursGansu, Shaanxi, Xinjiang, Anhui, and Ningxia8 hoursQinghai, Liaoning, and Jilin10 hoursHubei
After adjusting for duration, the relative compensation levels are:
Gansu > Liaoning > Jilin > Shaanxi = Xinjiang = Anhui = Ningxia (draft) > Qinghai > Hubei.
Gansu, Qinghai, and Liaoning have also published supply–demand adjustment factors below 1. Provincial performance assessment requirements further increase the importance of operating capability.
Chart. Comparison of capacity compensation revenues for four-hour storage systems.
Two distinctions are essential when evaluating these mechanisms.
First, Qinghai’s 8.75-hour average largely reflects solar PV projects paired with molten salt thermal storage and compressed air energy storage. Their project configurations and the peak-duration adjustment used for capacity payments relate to different mechanisms.
Second, generation-side storage paired with power generation is outside the capacity compensation scope discussed here. Its revenue model should therefore be assessed separately from eligible independent grid-side storage.
5. Technologies: LFP Leads, While Non-Lithium Long-Duration Storage Reaches 8.2%
Lithium iron phosphate batteries remained the dominant technology, accounting for 90.9% of newly commissioned power capacity.
Compressed air energy storage and molten salt thermal storage projects together represented 8.2% of additions. Several hybrid projects combining lithium-ion batteries with sodium-ion batteries or supercapacitors also entered operation.
Although 8.2% remains a relatively small share, the changing technology mix warrants attention. Capacity payment frameworks that adjust compensation according to peak-support duration may reshape the economics of long-duration storage.
The pipeline of compressed air and flow battery projects for 2027, together with the pace of capacity pricing implementation across more provinces, will be important indicators of long-duration storage’s progress toward larger-scale deployment.
Figure 6. Technology mix of newly commissioned new energy storage projects in China, October 2026, by power capacity.
Source: CNESA DataLink Global Energy Storage Database.
6. Three Signals to Watch
Duration is becoming a new dimension of competition.
When policy assigns value to discharge duration, investment incentives shift accordingly. October’s national average of 3.30 hours, generation-side average of 4.72 hours, Northwest China average of 4.34 hours, and East China average of 2.00 hours illustrate a changing competitive landscape.
The focus is moving from capital cost per unit of power capacity toward the ability to deliver dependable capacity during peak demand.
Project timing is playing a greater role in monthly deployment fluctuations.
Monthly changes increasingly reflect procurement schedules, year-end grid-connection deadlines, and project acceptance cycles, alongside underlying demand.
Meanwhile, four-hour system quotations moved higher in October, and battery cell prices continued rising during the year, indicating that upstream cost increases are being passed downstream.
Regional differences are likely to widen further.
Northwest China’s storage market is shaped by wind and solar resources and capacity compensation mechanisms. East China’s market is shaped by load density and opportunities arising from spot-market price spreads.
Differences in optimal discharge duration, revenue structures, and investor preferences are continuing to expand. National averages alone are no longer sufficient to describe the market.
For November, key developments to watch include whether the year-end grid-connection surge can lift annual installations to a new high, whether long-duration deployments continue in Gansu and Qinghai, and how provincial capacity payment eligibility lists are implemented.
Data source: CNESA DataLink Global Energy Storage Database. Statistics are based on incomplete project tracking.