The 2.4GWh Shared Energy Storage Site in Inner Mongolia Is Approved, And The Duration Is Designed to Be 2-4 Hours

On July 5, the Hohhot Development and Reform Commission approved the shared energy storage site in Hohhot Development and Reform Commission. The site owner is Inner Mongolia Zhongdian Energy Storage Technology Co., Ltd, and the site adopts a DC 1500V energy storage system solution with a total capacity of 2400MWh, which is planned to be divided into 480 units of 5MWh and constructed in two phases. The capacity of the first and second phases of the site is 1200MWh, and the land is 100,000 square meters. The project will be constructed in different zones, and the storage duration is designed to be 2-4 hours.